The activities for the Environmental Impact Assessment (EIA) Decision for the new nuclear power plant in Kozloduy are being successfully carried out.

Activities have commenced for the implementation of the monitoring network at the site approved for the deployment of the new nuclear blocks at the Kozloduy Nuclear Power Plant.

The team from the consortium „MSU - Energoengineering“ DZZD, selected to carry out the activities, must build a perimeter sampling network of 12 control points for monitoring and control of groundwater, atmospheric precipitation, soil, vegetation, passive monitoring of the gamma radiation background, and tracking changes in environmental parameters.

Each control point will consist of a deep hydrogeological borehole with a piezometer well for observations, an atmospheric deposition collector, a thermoluminescent dosimeter for gamma background monitoring, with two of these being equipped with a device for monitoring the seismic characteristics of the Earth's surface and a high-flow device to monitor airborne aerosol activity.

The monitoring network will upgrade the existing radioecological monitoring system of the Kozloduy NPP and at the same time will provide a database for the construction of new nuclear facilities on the site.

The activities for building a radioecological monitoring network are part of the „Programme for Continuous Monitoring of Site No. 2, approved for the placement of a new nuclear facility – a nuclear power plant“, developed and agreed with the Ministry of Environment and Water and the Nuclear Regulatory Agency. The quality of execution of the objectives set out in the Programme is a priority for „Kozloduy NPP – New Builds“ EAD, „Kozloduy NPP“ EAD and „MGU-Energoremont“ DZZD, because environmental protection is of paramount importance for all phases of the life cycle of the future new nuclear power facilities located on the site of Kozloduy NPP. By fulfilling the imperative obligations, conditions and measures laid down in the Order of the Nuclear Regulatory Agency for the approval of the site for a new nuclear power facility and the Environmental Impact Assessment Decision, „Kozloduy NPP – New Builds“ EAD, „Kozloduy NPP“ EAD and „MGU-Energoremont“ DZZD declare their serious approach and adherence to the latest standards in radioecological monitoring and environmental protection.


More messages

Safety is our No. 1 priority.

The development of new nuclear power capacity in Bulgaria is based entirely on strict adherence to the current Bulgarian and European regulatory framework, as well as the best international practices, including the standards of the International Atomic Energy Agency (IAEA) and the Western European Nuclear Regulators’ Association (WENRA). The chosen AP1000 technology of […]

1 May 2026 Read more

Information message

In fulfillment of Article 95, Paragraph 3 of the Environmental Protection Act (EPA) and in connection with Article 10 of the Ordinance on the Conditions and Procedure for carrying out Environmental Impact Assessment (EIA), „Kozloduy NPP – New Builds“ EAD publishes the Terms of Reference for the scope and content of the EIA report for the investment proposal

8 April 2026 Read more

„Kozloduy NPP – New Capacities has signed a contract for engineering and consultancy services for the new units.

„Kozloduy Nuclear Power Plant – New Capacities EAD marked an important milestone in the implementation of the project for the construction of Units 7 and 8 with the signing of an engineering and consulting services contract with a consortium of leading international companies: Laurentis Energy Partners, BWXT Canada Ltd., and Canadian Nuclear Partners.

2 December 2025 Read more