A five-member panel of the Supreme Administrative Court ruled that the Environmental Impact Assessment for the construction of a new nuclear power unit at Site 2 of the Kozloduy Nuclear Power Plant was lawful.„

A five-member panel of the Supreme Administrative Court rejected the appeals against Decision No. 1-1/2015 of the Minister of Environment and Water, which approved the environmental impact assessment in connection with the implementation of an investment proposal "Construction of a new nuclear power plant of the latest generation on Site 2 of the "Kozloduy NPP". This result was reached after the annulment of a decision of a three-member panel of May 17 last year, which annulled the assessment. The decision in administrative case No. 12369 of 2018 is final.

The five-member panel accepts that when issuing Decision No. 1-1/2015, the mandatory procedures under the EIA Regulation, including the Convention on Environmental Impact Assessment in a Transboundary Context, were complied with.

With regard to the issue raised by the applicants question of the long-term solution to the problem of spent nuclear fuel and radioactive waste, the court accepted that by law this is an obligation of a third party not participating in the administrative proceedings. The management of spent nuclear fuel, radioactive waste and related measures for environmental protection and protection of human life and health is within the competence of the State Enterprise "Radioactive Waste" by virtue of the law, and not of "Kosloduy NPP - New Capacity" EAD, which is the assignor of the investment proposal for the construction of a new nuclear capacity.

With regard to the issue raised by the applicants Site selection question 2, the cassation instance notes that the choice was made in accordance with the opinions of the team of specialized experts who prepared the EIA report, of the specialized departments, including those responsible for the protection of biological diversity and the protection of water resources, including "Water Supply and Sewerage" Ltd., Vratsa, which manages the water supply facilities in the area.

By the issue of groundwater monitoring, the court accepted that an explicit measure was foreseen as part of the already functioning monitoring system of the Kozloduy NPP. The five-judge panel also found that the report explicitly took a position on the impact on the protected fish species Alosa sp. and the invasive species Asian cortibulus, and specific protection measures were also foreseen. This issue was also raised in the public debate in the Republic of Romania, as well as mentioned in the opinion of the Directorate "National Service for Nature Protection".

This act of the Supreme Administrative Court once again confirmed the conscientious and highly professional attitude of the teams of "Kozloduy NPP" EAD and "Kozloduy NPP - New Build" EAD towards the activities for the responsible and sustainable development of nuclear energy.


More news

17 July 2026

The management of „Kozloduy NPP – New Builds“ and the US Embassy have confirmed the strategic partnership on the new nuclear power project.

The Board of Directors of „Kozloduy NPP - New Capacities“ held a working meeting with H. Martin McDowell, Chargé d'Affaires of the US Embassy in Sofia, and Mr. Patrick Tilou, Political and Economic Affairs Advisor to the US Embassy. The two sides declared their common commitment to the new nuclear power plant project in Kozloduy, which remains a strategic priority in [...]

Read more
14 July 2026

The executive director of „Kozloduy Nuclear Power Plant - New Powers“ Alexander Mihaylov held a meeting with MEP Tsvetelina Penkova on the future of nuclear energy.

The CEO of „Kozloduy Nuclear Power Plant - New Builds“ Alexander Mihaylov held a working meeting with Bulgarian MEP Tsvetelina Penkova. The two sides discussed the prospects for nuclear projects in the context of the intensifying European focus on energy security, industrial competitiveness, and decarbonisation.

Read more
9 July 2026

The new management of „Kozloduy NPP – New Capacities“ held its first working meeting with the senior management of the Westinghouse and Hyundai Engineering & Construction consortium.

On 9 July 2026, the new management of „Kozloduy NPP – New Capacities“ EAD held its first official working meeting with representatives of the senior management of Westinghouse and Hyundai Engineering & Construction (Hyundai E&C), dedicated to the development of the project for the construction of new nuclear capacities at the Kozloduy NPP site. From the company's side, it was attended by [...]

Read more
Change the Contrast

Customize this site to your preferences. It's easy, free, and anonymous.