02 Feb 2024
Kozloduy NPP-New Builds PLC informs that 5 companies have expressed interest in the procedure announced
by the company in regard with the construction of the 7th and 8th units at site No. 2 of our nuclear power plant
with AP-1000 technology. The procedure is pursuant of the decision of the National Assembly from 18.12.2023.
The application deadline expired on February 2, 2024 at 5:00 p.m. Commission will consider the documentation
applied since the beginning of the next week. Applicants are required to demonstrate construction experience
and commissioning of at least two nuclear units commissioned, to have solid experience in nuclear and turbine
island of at least two units or have supplied and installed equipment for two units within the last 15 years.
Applicants interested in the project should be able to demonstrate at least 6 billion dollars in turnover and profit
for the five years period from 2018 to 2022.