The five-member composition of VAS has ruled the legality of the EIA for the construction of new nuclear power on site 2 of Kozloduy NPP
The five-member Chamber of the Supreme Administrative Court dismissed the appeals against decision No 1-1/2015. Of the Minister of Environment and Water, which approved the environmental impact assessment in connection with the realization of an investment proposal "construction of a new nuclear power from the latest generation at the Kozloduy NPP site 2. This result was reached after the annulment of a decision of a three-member Chamber of 17 May M, which annulled the assessment. Decision on Adm. Case no 12369, 2018. is final.
The five-member group considered that in the issuance of decision No1-1/2015, the obligatory procedures of the EIA Ordinance were complied with, including Environmental impact assessment in a cross-border context.
As regards the question raised by the appellants as to the long-term solution to the problem of irradiated nuclear fuel and radioactive waste, the Court held that, by law, it was the duty of a third party neučastvaŝo in the administrative procedure. The management of spent nuclear fuel, radioactive waste and environmental measures related to this activity and the protection of human life and health is within the competence of state-owned enterprises "Radioactive waste" under The law and not the Kozloduy NPP – new capacities EAD, which is the contracting authority of the investment proposal for the construction of new nuclear power.
As regards the question of choice of site 2 posed by the appellants, the Cassation Court observes that the choice was made in accordance with the opinions of the team of specialised experts drawn up the EIA report, the specialised Departments, including those responsible for the conservation of biological diversity and for the protection of water resources, including and "water supply and sewerage" LTD., Town of Vratsa, which manages the water supply facilities in the area.
On the subject of groundwater monitoring, the Court considered that an explicit measure was envisaged as part of the already functioning monitoring system for Kozloduy NPP. The five-member Chamber also finds that the report has explicitly taken an opinion on the impact on the protected species of Alosa sp. and invasive species of Asian kortibula, with specific protection measures foreseen. This question was also put to the public consultation in the Republic of Romania, as well as the opinion of the National Office for Nature Protection.
With this Act YOU once again confirm the conscientious and high professional attitude of the teams of Kozloduy NPP PLC and Kozloduy NPP-new capacities EAD to the activities for the responsible and sustainable development of nuclear energy.
Kozloduy NPP – New Build implements an environmental monitoring network at the approved site
The project company Kozloduy NPP - New Build. continues with the implementation of the imperative requirements, conditions and measures set in the Order of the Bulgarian Nuclear Regulatory Agency (BNRA) for approval of the site for the nuclear facility and the...
The development of the Detailed Development plan of the New Build Site has been started
On the 31th of March 2021 the Project company “Kozloduy NPP- New Build” Plc assigned to “Geoconsult” Ltd the elaboration of a Detailed Development plan for the territory of the approved site for the construction of a new nuclear power capacity. These activities will...
The Council of Ministers takes a decision for full capacity use of the approved Kozloduy NPP site, through rational use of the equipment for Belene NPP
On January 20, 2021, at its meeting, the Government has considered a report of a Working Group specially set up by the Minister of Energy. In the report in a synthesized manner, the analyzes and assessments of the feasibility studies carried out by Kozloduy NPP - New...
Official USA Visit in NPP Kozloduy
Her Excellency Ambassador Hero Mustafa and her team visited the Kozloduy NPP in the context of the Memorandum of Understanding on the Civil Nuclear Power Network, signed between the United States and Bulgaria on October 23rd. The purpose of the visit was to get...
Supreme court reject all appeals against EIA
Following an extraordinary and final judicial control before the Supreme Administrative Court, no infringements were found in the legally conducted EIA procedure of the investment proposal for the construction of a new nuclear power unit from latest generation at the...
Еlaboration of a Detailed Structural Plan
During the regular meeting of the Council of Kozloduy Municipality on 13th August 2019 the unanimous decision was authorized in a relation with the elaboration of a Detailed Structural Plan of the site which is suitable for constructing of a new nuclear power...
Kozloduy NPP-New Build presented a report on the Convention on Nuclear Safety
Kozloduy NPP PLC has prepared and provided to the Nuclear Regulatory agency information on the preparation of the eighth national report of the Republic of Bulgaria under the Convention on Nuclear Safety, within the limits of its competencies. The information shall...