China starts construction of new SMR

The Chinese Ministry of Environment has proceeded to assess the environmental impact of a project to build a small modular reactor ACP100 (SMR) in Changjiang, Hainan, as the construction will commence by the end of this year.

According to the Chinese edition Nuclear World, the first concrete should be poured on December 31. The construction is expected to take 65 months, with 125 MWe power expected to enter into service until 31 May 2025, subject to appropriate governmental approvals.

ACP100 has been identified as a “key project” in China’s 12th five-year plan and is a modification by the larger reactor with pressurized water ACP1000 (PWR). The design, which has 57 fuel cartridges and integrated steam generators, includes passive safety features and will be installed underground. China in 2016. Announced plans to build a demonstration floating nuclear power plant based on ACP100S.

The two-element demonstration installation was originally planned for construction by CNNC New Energy Corporation, a joint venture of CNNC (51%) and China Guodian Corp. In the beginning of 2017, the The site for the first units ACP100 was changed to Changjiang, the island of Hainan, with a larger reactor, which will be built in Putian.

The small module reactor ACP100 will be located in the northwest of the existing nuclear power plant in Yangjiang. On the site there are already two working CNP600 PWR, with plans for the development of two more reactors of this type.

ACP100 is planned to be serially produced as industrial generating capacity, such as urban DHC, for desalination of seawater, and for the extraction of energy on floating platforms (see illustration).

China starts construction of new SMR

The Chinese Ministry of Environment has proceeded to assess the environmental impact of a project to build a small modular reactor ACP100 (SMR) in Changjiang, Hainan, as the construction will commence by the end of this year. According to the Chinese edition Nuclear...

Kozloduy NPP-New Build presented a report on the Convention on Nuclear Safety

Kozloduy NPP PLC has prepared and provided to the Nuclear Regulatory agency information on the preparation of the eighth national report of the Republic of Bulgaria under the Convention on Nuclear Safety, within the limits of its competencies.
The information shall include a summary of the activities carried out in the company, in accordance with the international requirements related to maintaining a high level of safety culture.
Last but not least is marked the status of the project for the construction of new nuclear power on the site of Kozloduy NPP.
We remind that at the moment the project is at the final stage of the pre-project phase according to the project plan, namely the issuance of an order for approval of the selected site, the documents for the same are examined and no notes are found to Prevent the issue.

At the end of 2018, a reassessment of the company’s assets, showing sound financial management of capital funds and strict adherence to the principles of sound corporate governance of the European Union, was drawn up pursuant to Regulation 2067/2016. The project company. A decision of the second-instance Chamber of the VAS is expected, related to the case against the decision of the Minister of Environment and Water, which approved the investment proposal for the construction of new nuclear power at the site of Kozloduy NPP.

Information notice

16 Feb 2024 Pursuant to the Decision of the National Assembly dated 18.12.2023 (published in State Gazette №105/2023) for taking actions for the construction of units 7th and 8th at site No. 2 of the Kozloduy NPP, on 19.01.2024 ‘Kozloduy NPP - New Builds’ PLC...

Information notice

19 Jan 2024 In pursuance of "Decision of the Parliament dated 18.12.2023 (published State Gazette 105/2023) for taking actions for the construction of 7th and 8th unit at site № 2 of NPP Kozloduy with АР 1000 technology", Kozloduy NPP - New Builds PLC publishes an...

Official USA Visit in NPP Kozloduy

Her Excellency Ambassador Hero Mustafa and her team visited the Kozloduy NPP in the context of the Memorandum of Understanding on the Civil Nuclear Power Network, signed between the United States and Bulgaria on October 23rd. The purpose of the visit was to get...

Supreme court reject all appeals against EIA

Following an extraordinary and final judicial control before the Supreme Administrative Court, no infringements were found in the legally conducted EIA procedure of the investment proposal for the construction of a new nuclear power unit from latest generation at the...

Еlaboration of a Detailed Structural Plan

During the regular meeting of the Council of Kozloduy Municipality on 13th August 2019 the unanimous decision was authorized in a relation with the elaboration of a Detailed Structural Plan of the site which is suitable for constructing of a new nuclear power...